| Project Name: |
Water Line Replacement |
| Customer: |
City of Glendale - Glendale, AZ |
| Market: |
City and Municipality |
|
|
| Scope: |
Centennial provided the scope of work and drawings for this pipeline project and reviewed them with the Owner. This was a very schedule sensitive project and the condition of the existing
water line was unknown. CCE also pre-priced an alternate to replace the existing RCP casing if required. The end-user was a new retail store requiring the water line in service by 1/1/03. The Owner issued CCE the notice to proceed and the work was completed ahead of the agreed upon 40 calendar day schedule. |
| Summary: |
- On Budget
- 2 days ahead of schedule
- 1 Owner-requested change order
- Zero punch list
|
|
Click here for a printable version of this profile
|